Total Gas & Power North America Inc. v. Federal Energy Regulatory Commission

Certiorari Denied

Petition for certiorari denied on June 18, 2018.

Docket No.17-975
Op. Below5th Cir.

Issue

Whether forcing an entity to defend claims for civil liability and penalties in an ultra vires agency proceeding, when "exclusive jurisdiction" of those claims lies in federal district court, presents a ripe case or controversy under Article III and the Declaratory Judgment Act as to the proper forum for adjudication.

Proceedings & orders timeline

Oct 27, 2017
Application (17A477) to extend the time to file a petition for a writ of certiorari from November 6, 2017 to January 5, 2018, submitted to Justice Alito.
Oct 30, 2017
Application (17A477) granted by Justice Alito extending the time to file until December 6, 2017.
Nov 22, 2017
Application (17A477) to extend further the time from December 6, 2017 to January 5, 2018, submitted to Justice Alito.
Nov 22, 2017
Application (17A477) granted by Justice Alito extending the time to file until January 5, 2018.
Jan 5, 2018
Petition for a writ of certiorari filed. (Response due February 8, 2018)
Feb 6, 2018
Motion to extend the time to file a response from February 8, 2018 to March 12, 2018, submitted to The Clerk.
Feb 7, 2018
Motion to extend the time to file a response is granted and the time is extended to and including March 12, 2018.
Mar 9, 2018
Motion to extend the time to file a response from March 12, 2018 to April 11, 2018, submitted to The Clerk.
Mar 12, 2018
Motion to extend the time to file a response is granted and the time is further extended to and including April 11, 2018.
Apr 9, 2018
Motion to extend the time to file a response from April 11, 2018 to May 11, 2018, submitted to The Clerk.
Apr 10, 2018
Motion to extend the time to file a response is granted and the time is further extended to and including May 11, 2018.
May 11, 2018
Brief of respondents Federal Energy Regulatory Commission, et al. in opposition filed.
May 11, 2018
Brief of Federal Energy Regulatory Commission, et al. in opposition not accepted for filing. (May 11, 2018)
May 11, 2018
Brief of Federal Energy Regulatory Commission, et al. in opposition not accepted for filing. (July 23, 2018)
May 25, 2018
Reply of petitioners Total Gas & Power North America, Inc., et al. filed.
May 29, 2018
DISTRIBUTED for Conference of 6/14/2018.
Jun 18, 2018
Petition DENIED.