Sandy Creek Energy Associates, L.P. v. Sierra Club, Inc.

Pending Petition
Docket No.10-1333
Op. Below5th Cir.

Issue

Whether, after construction of a power plant has begun in reliance on the issuance of a lawful preconstruction permit reflecting that there was no Maximum Achievable Control Technology ("MACT") requirement then in force, a new MACT determination requirement can be compelled during construction, contrary to EPA regulations and judicial interpretations of closely related provisions of the Clean Air Act.