TAMKO Building Products, Inc. v. Hobbs
Petition for certiorari denied on May 22, 2017
Docket No. | Op. Below | Argument | Opinion | Vote | Author | Term |
---|---|---|---|---|---|---|
15-1318 | Mo. Ct. App. | N/A | N/A | N/A | N/A | OT 2016 |
Issue: Whether a state court can evade the preemptive force of the Federal Arbitration Act by framing its refusal to enforce an arbitration agreement as a product of supposed defects in "contract formation" that would not prevent the formation of any other contract.
Date | Proceedings and Orders |
---|---|
04/25/2016 | Petition for a writ of certiorari filed. (Response due May 27, 2016) |
05/18/2016 | Waiver of right of respondents Lee Hobbs, et al. to respond filed. |
06/07/2016 | DISTRIBUTED for Conference of June 23, 2016. |
06/15/2016 | Response Requested . (Due July 15, 2016) |
07/11/2016 | Order extending time to file response to petition to and including September 13, 2016. |
09/13/2016 | Brief of respondents Lee Hobbs, et al. in opposition filed. |
09/27/2016 | Reply of petitioner TAMKO Building Products, Inc. filed. |
09/28/2016 | DISTRIBUTED for Conference of October 14, 2016. |
10/24/2016 | DISTRIBUTED for Conference of October 28, 2016. |
05/15/2017 | DISTRIBUTED for Conference of May 18, 2017. |
05/16/2017 | Supplemental brief of petitioner TAMKO Building Products, Inc. filed. (Distributed) |
05/17/2017 | Supplemental brief of respondents Lee Hobbs, et al. filed. (Distributed) |
05/22/2017 | Petition DENIED. |